Task or Out Turn Work



The capacity of Doing work by skilled labor in the form of quantity per day is called task or out turn work.

Some of the task of major construction activities has been listed below:

Particulars of  Item Qty  Unit Per Day
A. Brickwork
1 Brickwork in Lime or Cement Mortar ( Foundation & Plinth) 1.25 Cum Per Mason
2 Brickwork in Lime or Cement Mortar (Super structure) 1 Cum Per Mason
3 Brickwork in Mud Mortar ( Foundation & Plinth) 1.5 Cum Per Mason
4 Brickwork in Mud Mortar (Super structure) 1.25 Cum Per Mason
5 Brick in Cement or lime mortars in arches 0.55 Cum Per Mason
6 Brick in Cement or lime mortars in Jack arches 0.55 Cum Per Mason
7 Half Brick wall in Partition (115 mm)
B. Stone Work 
8 Course Rubble Stone Masonary in lime/cement mortar + dressing 0.8 Cum Per Mason
9 Random Rubble Stone Masonary in lime/cement mortar + dressing 1 Cum Per Mason
10 Ashlar Masonary in lime/cement Mortar 0.4 Cum Per Mason
11 Stone  Arch Work 0.4 Cum Per Mason
C. Concrete Work
12 Lime concrete in foundation/ floor 8.5 Cum Per Mason
13 Lime concrete in roof terracing 6 Cum Per Mason
14 Cement concrete (1:2:4) 5 Cum Per Mason
15 R.B. work 1 Cum Per Mason
16 R.c.c work 3 Cum Per Mason
D. Plastering work
17 Plastering (12mm)with cement/ lime mortar 8 Cum Per Mason
18 Pointing with Cement/ Lime mortar 10 Cum Per Mason
E. Whitewashing or Painting
19 Whitewashing or Colour Washing - 1 coat 200 sqm per White Washer
20 Whitewashing or Colour Washing - 3 coats 70 sqm per White Washer
21 Door / Windows painting or varnishing- 1 Coat 25 sqm per painter
22 Painting large surface -1 Coat  35 sqm per painter
23 Distempering - 1 coat 35 sqm per painter
F. Flooring
24 2.5 cm ( 1 inch) C.C. floor 7.5 sqm Per Mason
25 Flagstone floor laying with lime/cemnt mortar excluding L.C. 10 sqm Per Mason
26 Terazzo flooring (6mm thick mosaic work) over 2 cm thk Cement concrete (1:2:4) 5 sqm Per Mason
27 Brick on edge in floor lime/cement mortar excluding L.c.  7 sqm Per Mason
28 Brick flat floor lime/cement mortar excluding L.c.  8 sqm Per Mason
G. Door Frame
29 Timber Framing (Sal/ Teak wood) 0.07 cum per carpenter
30 Timber Framing (Country wood) 0.15 cum per carpenter
D/W Shutters
31 Door/ window shutters panelled or glazed  0.15 sqm per carpenter
32 Door/ window shutters battened 0.8 sqm per carpenter
33 Sawing Hard  wood 4 sqm per pair of sawers
34 Sawing Soft  wood 6 sqm per pair of sawers
 H. Tiling
35 Single Allahbad/ Mangalore tiling 6 sqm Per Tile layer
36 Double allahbaad tiling 4 sqm Per Tile layer
37 Breaking of brick ballast 
a 40 mm Gauge 0.75 Cum Per Labor
b 25 mm Gauge 0.55 Cum Per Labor
38 Breaking of  Stone ballast 
a 40 mm Gauge 0.4 Cum Per Labor
b 25 mm Gauge 0.25 Cum Per Labor
 I. Dressing Work
43 Ashlar Stone dressing 0.7 cum Per stone cutter
44 Flag stone dressing 1.5 sqm Per stone cutter
 J. Earth Work
45 Earthwork in excavation in ordinary soil 3 cum per labor
46 Earthwork in excavation in hard soil 2 cum per labor
47 Excavation in rock  1 cum per labor
48 Sand filling in plinth 4 cum per labor

11 comments:

  1. Thanks for sharing the post.. parents are worlds best person in each lives of individual..they need or must succeed to sustain needs of the family.
    St.Louis

    ReplyDelete
  2. Hi sir , realluy a mason can do 8cum of cement moratar in plastering ? or it is 8 sqm , i wonder 8 cum of mortar will cover more than 600sqm of area , can you pls explain it .. thanks

    ReplyDelete
  3. Painter200sq.m.. Not possible.. Something wrong..

    ReplyDelete

  4. Hi Very Nice Blog I Have Read Your Post It Is Very Informative And Useful Thanks For Posting And Sharing Sellers as well as suppliers of construction material& building offers the highest quality of Exdesign Build for the sale to industries &people that needs to construct flat, home, office, retail store or for the existing building. Find here online price details of companies selling Brick Tile. Get info of suppliers, manufacturers, exporters, traders of Masonry Tiles for buying in Singapore

    ReplyDelete
  5. You can read more about civil engineering knowledge here :- www.civilconcept.com

    ReplyDelete
  6. I really appreciate admin for such article which will be very informative for the viewers. Thank you so much.
    Brooklyn brownstone renovation contractors,

    ReplyDelete

Task or Out Turn Work (Labor output)

Task or Out Turn Work The capacity of Doing work by skilled labor in the form of quantity per day is called task or...